| Assess project status and identify any blocking issues and opportunities. Identify and manage exceptions, problems, and risks. Communicate project status. | 
 
| Disciplines: Project Management | 
 
 
 | 
 
 
 
Purpose 
    To help the team meet the iteration objectives and keep the project on track. Manage stakeholders'
    expectations as technical and practical discoveries are made during the project.
  | 
 
 
 
Relationships 
| Roles | Primary Performer:
								
 | Additional Performers:
								
 | 
 
| Inputs | Mandatory:
								
 | Optional:
								
 | 
 
| Outputs | 
 | 
 
 
 
Main Description 
    Developing the team is part of executing the project. The project manager is responsible for improving the interactions and trust 
    between team members, incorporating team building into project activities, and empowering the
    team to make decisions. Management is done by objectives and not by time reporting.
 
    The project manager helps the team meet the iteration objectives by removing constraints, and by monitoring the progress
    and work remaining to completion. When the team is falling behind, the project manager helps the team
    assess how it can reduce work and still meet the iteration goals. Involve stakeholders in approving changes and actions
    that affect them, so that their objectives for the iteration can be met, and the issues they raise can be solved throughout
    the iteration.
  | 
 
 
 
Steps 
| 
 Track current iteration progress 
    Continuously monitor the iteration to ensure that it is progressing appropriately. Track the progress of the current
    iteration by maintaining visibility on the status of the items that are being worked on during the iteration. In
    particular, it is important to be able to understand how quickly the team is moving through the work scheduled for the
    iteration, and how accurate the estimates were [LEF07].
 
    Share information about the progress being made by having quick, frequent meetings with the entire project team. These
    meetings are useful to understand what team members have accomplished since the last meeting, and what they plan to
    accomplish before the next meeting. It also allows the team to identify any blocking issues. See [Collaboration Guidance] for more information.
 
    Track the status of each work item by using visual indicators of state information (for example: defined, completed,
    accepted) in a wall or automated tool. Since iterations are typically fixed in duration, another primary way to
    gauge progress is to continuously monitor current status and also estimate how much work remains. Plot an
    iteration burndown chart on a daily basis in order to visualize progress on a given iteration. This chart is plotted
    with the total estimates for all the items that are not yet started and the estimated remaining effort for any item in
    progress. See Report: Iteration Burndown for more information.
 
    Take corrective actions to adjust the course of the iteration if the burndown chart shows that the work will not be
    finished as planned.
  | 
 
 
 
Capture and communicate project status 
    Because outside stakeholders do not participate in the daily activities of the team, it is important that the status of
    the project should be communicated to them as often as possible. This communication significantly lowers
    the risk of disconnect between the development team and the stakeholders. The status provides the team with
    data they can use to improve their development process.
 
    Besides the iteration status, the overall project status can be captured and communicated in
    a burndown report for the whole project. This report should show the progress toward the release
    date, and should be updated at the end of every iteration (when metrics, such as the team's velocity, can also be
    provided). This allows the team to predict what it can accomplish on the remaining project iterations. Other
    metrics (such as number of test cases passed) can also be used to present iteration and project status.
 
    Keep the status information visible to stakeholders and the project team at all times in a project workspace (walls or
    automated tool), where stakeholders can come and experience first-hand the progress being made by the team.
  | 
 
 
 
Handle exceptions and problems 
    One of the project manager's key responsibilities is to know about the project team's problems and issues. The manager
    needs to focus on problems that are blocking progress. A quick, daily meeting is usually a good way to monitor those
    problems and issues. A record of issues that have to be solved within the team may be kept in the Iteration Plan. If a critical problem or
    issue is likely to take a lot of time to solve, capture it in the Work Items List so that it can be assigned to an
    individual.
 
    Identify the cause and impact of problems and exceptions as they arise. Identify possible solutions for problems that
    have an immediate impact on the short-term goals and objectives. Identify who needs to be involved in implementing
    the solution. Define the corrective actions and implement them.
  | 
 
 
 
Identify and manage risks 
    Identify risks as soon as the project starts, and continue identifying and managing risks throughout the project. The Risk List should be revisited weekly, or at a minimum once per iteration. The
    entire team should be involved in identifying and mitigating risks.
  | 
 
 
 
Manage objectives 
| When a team is falling significantly behind, or critical problems occur that prevent the team from meeting the
iteration objectives, it may be necessary to descope work to ensure that the team delivers a useful product increment by
the end of the iteration, while maximizing stakeholder value. The project manager should work with the team and
stakeholders to revise the Iteration Plan and, as necessary, reduce the emphasis on less critical tasks by postponing
them to a subsequent iteration. In rare cases, if the iteration objectives still seem impossible to meet, the team might
consider terminating the iteration or reformulating the iteration to a new objective. | 
 
 
 
 | 
 
 
 
Key Considerations 
    Select an approach for the collection of basic metrics: ideally, they are automatically generated from the tools at
    hand, but can be manually assembled, or both. Outline
    which metrics the project should use in the [Project Definition and Scope].
  | 
 
 
 
More Information 
 |